| Phase | Task | Date(s) | Owner | Status | Notes |
| 1: Concept | | | | | |
| | Identify and evaluate potential concepts using appropriate tools. Select concept that meets most requirements. | 2008/2/21 | Will | Done | |
| | Product Requirement Document (PRD) | 2008/3/13 | Will | | |
| | PRD Review | 2008/3/20 | Team | | |
| | Documnet Product Concept Document (PCD) | 2008/3/27 | Charles | | |
| | PCD Review | 2008/4/4 | Team | | |
| 2: Plan | | | | | |
| | Document product architecture, external interfaces, compatibility and interoperability matrix, and internal interfaces into a draft Functional Specification Document (FSD). | 2008/5/8 | Software(Leon)/Hardware(Will) | | |
| | FSD Review | 2008/5/22 | Team | | |
| 3: Develop/ Integrate/ Test | | | | | |
| | Compile initial draft of Design Specifications. | 2008/6/5 | | | |
| | Begin design of all internal components and system. | 2008/6/12 | | | |
| | Finalize and vault all component design documentation. | 2008/7/17 | | | |
| | Power-on.(Hello World) | 2008/10/16 | | | |
| | File bugs; ensure Root Cause & Corrective Action (RCCA) are completed for each bug. | 2008/11/20 | | | |
| 4: System Test | | 2008/??/?? | | | |
| 5: Customer Acceptance | | 2008/??/?? | | | |
| 6: Deploy | | 2008/??/?? | | | |
| 7: Sustain | | 2008/??/?? | | | |