| Phase | Start | End | Status | Actual |
| Phase 1: Gap Analysis | Jan 30 | Feb 9 | Done | Feb 22 |
| Phase 2: Detailed Gap Analysis and SW Development | Mar 13 | Sept 13 | In Progress | |
| -------Iteration 1: Development of FS | Mar 13 | Mar 29 | Completed | |
| -------Iteration 1: S/W Development | Apr 2 | May 9 | | |
| ++++Iteration 2: Development of FS | Mar 30 | Apr 25 | | |
| ++++Iteration 2: S/W Development | May 10 | Jul 4 | | |
| -------Iteration 3: Development of FS | Apr 26 | May 3 | | |
| -------Iteration 3: S/W Development | Jul 4 | Jul 19 | | |
| ++++Iteration 4: Development of FS | May 4 | May 21 | | |
| ++++Iteration 4: S/W Development | Jul 20 | Sept 11 | | |
| Phase 3: Data Migration | Aug 20 | Sept 28 | | |
| Phase 4: Training Users | Sept 17 | Sept 28 | | |
| Phase 5: Deployed at 1 Branch, Parallel Run | Oct 1 | Dec 31 | | |
| Phase 6: Rollout across all branches | Jan 1, 08 | Feb 4, 08 | | |